SUE ยท Standards

What a utility quality level actually promises

QL-A, QL-B, QL-C and QL-D under ASCE 38 are not grades of effort. They say where the information came from โ€” and only one means the pipe has been seen.

July 16, 2026 · 6 min read

A utility drawing arrives with everything on it drawn the same way. Every line the same weight, every service the same colour convention, nothing to say which of them somebody actually found and which were copied off a record that may predate the works. The crew digs with the confidence the drawing projects rather than the confidence the data supports, and the difference between those two things is where strikes happen.

ASCE 38-22 exists to close that gap. It defines four quality levels, and the thing most people get wrong about them is this: they are not grades of effort, and they are not a ranking of how carefully anyone worked. They describe where the information came from.

The four levels at a glance

ASCE 38 sets out four levels. They are not a ladder of thoroughness — they are a statement about the origin of the information, and what it is therefore safe to do with it.

Utility quality levels under ASCE 38. QL-B is designating; QL-A is locating. Only QL-A rests on anyone having seen the utility.
LevelAlso called Where the information comes fromWhat you actually get
QL-DRecords research Utility owner records, as-builts, oral accounts An indication that something may be there
QL-CSurveyed surface features QL-D, plus visible surface features surveyed — manholes, valve covers, pedestals Records correlated to things you can stand next to
QL-BDesignating Surface geophysics — electromagnetic locating and radar Horizontal position of the utility, marked and surveyed
QL-ALocating Physical exposure, usually by vacuum excavation Measured horizontal and vertical position, with size and material

The gap that matters is between QL-B and QL-A. QL-B tells you where a line runs across the ground. It does not tell you how deep it is to survey accuracy, and a depth figure annotated on a QL-B mark is an estimate from the instrument, not a measurement of the pipe.

QL-D — from the records

Existing records: utility owner drawings, one-call tickets, as-builts, GIS layers held by a municipality. Nobody has been to site.

QL-D is as good as the records, which on a site developed before the 1980s means it may be substantially wrong. Lines get abandoned without the drawing being updated. Services get rerouted during construction and the as-built never catches up. Private networks — the ones inside a property boundary, owned by the occupier rather than a utility — frequently appear on no record at all.

It is still worth having. It tells you what to expect and what to ask about. It is not a basis for excavation.

QL-C — records correlated with surface features

Somebody walks the site and ties the records to what is visible: manhole and valve covers, meter pits, poles, lamp standards, marker posts. Where a recorded line runs between two visible structures that belong to it, that line gains real support. Where it does not, the discrepancy is visible.

QL-C is the level most likely to be mistaken for something stronger, and it is worth understanding why. The surveyed points are real. The manhole was found, occupied and coordinated, and that position carries genuine survey accuracy. So the drawing looks authoritative — proper coordinates, proper symbols, a surveyor's title block.

But the line drawn between two surveyed manholes is an assumption that the pipe runs straight between them. Often it does. Where it bends around an obstruction that was there in 1962 and is not there now, it does not, and nothing on the drawing says so.

QL-B — designated by geophysics

Horizontal position established by surface instruments: electromagnetic locating where the line is conductive and traceable, radar where it is not, and the position marked on the ground and surveyed.

This is the level most projects actually need, and it is where the real work is. It is also the level at which an honest practitioner starts distinguishing between findings. A live main traced by direct connection along its length, confirmed on two passes, is not the same object as a linear anomaly inferred from a single radar line across a congested backfill — and a QL-B drawing should say which is which.

What QL-B does not give you is depth. Depth from an electromagnetic locator is computed from the field shape and is distorted by adjacent services, by congestion, and by the current finding a path along something other than the target. Depth from radar depends on an assumed velocity unless something of known depth was available to calibrate against. Both produce a number. Neither number is a measurement in the sense a designer means.

QL-A — the pipe has been seen

A test hole is excavated, usually by vacuum excavation, and the utility is physically exposed and measured. Horizontal and vertical position to survey accuracy, plus the thing no surface method can give you: what the pipe is actually made of, what diameter it actually is, and what condition it is in.

Only QL-A involves anyone seeing the utility. Everything above it is inference from a measurement, and the four levels exist precisely so that distinction survives onto the drawing instead of being flattened out of it.

The mistake that costs money

It is not commissioning the wrong level. It is commissioning one level and using the drawing as though it were another.

A QL-B drawing used to set a bore depth is the common version. The designation is correct — the line is where the survey said it was, horizontally. The depth annotation is an estimate carried along for reference, and somewhere between the survey and the bore it stopped being read as an estimate.

This is why the quality level has to be stated on the drawing, per feature, rather than named once in a cover letter nobody reads at the trench. Mixed-level drawings are normal and perfectly proper — most sites end up with QL-B through the works area and QL-C or QL-D beyond it. What is not proper is a drawing where you cannot tell which is which.

What to ask for

Specify the quality level you need, per area rather than per site. Ask for it stated per feature on the deliverable. Ask what happens where the method fails — because on reinforced concrete, in heavy wet clay, or over a non-conductive pipe in consolidated backfill, it sometimes will, and the honest answer is a gap on the drawing rather than a line drawn to fill it.

And where a design decision turns on depth, budget for QL-A at those specific points. Not across the site — that is rarely affordable or necessary — but at the crossings, the connections and the tie-ins where being wrong is expensive.

Utility locating and subsurface utility engineering →